Construction at Apollon Nessebar remains on schedule as winter begins.
The calendar winter has begun, but there is still no snow at Apollon. This allows construction of the new Apollon Nessebar development to continue at full speed.
In sections A and B, the reinforced-concrete structure has reached the fifth floor. In sections C and D, the underground parking, the slab above it and the first-floor columns are complete. Work on the underground parking is underway in section E.
Brickwork on the exterior and interior walls has also begun. The first-floor walls are complete in sections A and B, while work continues on the second floor of section A.
Construction remains on schedule. A contract for electrical installation work at the new site was signed the previous week.